Part of our guide: Hiring a general contractor in Louisiana: New Orleans, Baton Rouge, Lafayette, Lake Charles and Shreveport · Service page: Historic restoration
Who issues a New Orleans building permit
In Orleans Parish, the city's Department of Safety and Permits issues the building permit, plus electrical and mechanical ones. You apply online through the One Stop App, and the office is at 1340 Poydras Street, Suite 800. Plumbing is the odd one out: the city's guide to building permits says a plumbing permit comes from the Sewerage and Water Board.
Older neighborhoods add a layer. The Historic District Landmarks Commission (HDLC) reviews exterior work in local historic districts and on landmarks, and the Vieux Carre Commission (VCC) reviews work in the French Quarter. Both start from the same One Stop application.
What about the new permitting concierge you may have read about? In September 2026, Fox 8 reported that Safety and Permits would assign two staffers, starting in October, to walk business owners through city approvals. It's a pilot for businesses along the Chef Menteur Industrial Corridor and the Canal Corridor, and the city says it plans to expand. Nothing in the announcement covers homeowners, so a residential permit still goes through One Stop the usual way.
This guide sums up the official pages as of November 2026. Fees and procedures change, so check the linked page before you apply. For background on historic review, see HDLC Permits 101 and our permits and codes hub.
What work needs a building permit
Assume yes. The New Orleans building code, as quoted in the city's guide, requires a permit to construct, enlarge, alter, repair, move or demolish a building or structure, or to change its occupancy. New construction, additions and structural renovations also need plans stamped by a Louisiana-licensed architect or civil engineer.
The city does publish a short list of exempt work. It includes:
- Replacing less than 50 percent of the deteriorated siding on any one exterior wall
- Replacing deteriorated floorboards
- Replacing open, uncovered porches and steps 5 feet or less above grade
- Interior painting, papering and similar finish work
- Exterior painting and stucco repair that need no scaffolding over public property and no lead-paint removal
- Replacing less than 50 percent of the roofing or gutters on a one- or two-family home
- Fences up to 7 feet and retaining walls up to 3 feet that meet zoning
- Uncovered, detached decks up to 200 square feet and 30 inches high that aren't an exit
Exempt doesn't mean anything goes
The same list carries three warnings. Sheathing replacement isn't exempt, because the city treats plywood sheathing as structural. A roof over an open porch, with its framing, isn't exempt either. And skipping the permit doesn't excuse the work from the code, the HDLC or the VCC.
That last one catches people in historic districts. The HDLC says replacing deteriorated weatherboards, paving a yard or building a fence can still need a Certificate of Appropriateness when it's visible from the street, even with no permit required by Safety and Permits.
Trade permit and re-roofing permit rules
Trade work gets its own permit, and only a licensed trade can pull it. From the city's guide:
- Electrical: you need a permit to install, repair, replace or alter electrical equipment, bulbs and fuses aside. Only a Class A licensed city electrical contractor can apply.
- Mechanical: HVAC, heaters, furnaces and gas lines need a permit pulled by the right city-licensed contractor.
- Plumbing: removing or replacing water piping or fixtures needs a Sewerage and Water Board permit, and only an Orleans Parish licensed master plumber can apply.
- Re-roofing: a single- or two-family home needs a separate residential re-roofing permit when the work affects 50 percent or more of the roof. Bring a geotagged photo of the house and an estimate or contract signed by you and the contractor. As of the city's re-roofing page (updated October 28, 2026), the base fee is $60, plus $30 in a historic district, and review typically takes 2 to 4 days.
Historic review: HDLC and VCC
Is your house in a local historic district, or is it a landmark? Then plan the historic review before you plan the schedule. The HDLC says a Certificate of Appropriateness is required for exterior work on every building in its districts: repairs, alterations, additions, demolition, relocation and new construction. Painting generally doesn't need one, unless it's previously unpainted brick or involves changes to weatherboards. Look up your address on the HDLC's landmarks and districts map.
HDLC review runs at three levels. Staff can approve work that meets the design guidelines. Some work goes to the Architectural Review Committee, and the applicant has to attend. Demolition, new construction and keeping work done without approval usually go to the full Commission. The HDLC charges no fee of its own; instead, Safety and Permits adds a 50 percent surcharge to the permit and plan review fees.
In the French Quarter, the VCC's application process covers all exterior work, old or new. That includes painting, courtyard paving, fencing and roofing, even when no building permit is needed. Interior work that affects the structure goes to the VCC too. Start by finding the building on the VCC color rating map, which sets how strict the review is.
How long a permit and review take
Only some steps have published times, and they're estimates, not promises. Here's what the city states as of November 2026:
- HDLC staff review: about 3 to 5 days for a Certificate of Appropriateness, the HDLC says.
- HDLC Express Lane: the Express Lane issues certificates within 1 to 3 business days for qualifying work, such as roof replacement (FORTIFIED roofing included), repairs to match existing, HVAC, gutters, shutters, fencing and solar. The work has to meet the guidelines, the application has to be complete, and the property can't have other open violations.
- VCC staff review: staff usually issue a permit for routine work within 2 to 7 working days. Anything headed to the VCC Architectural Committee must be filed at least two weeks before its next meeting.
- Residential re-roofing permit: typically 2 to 4 days, and longer in historic districts.
- Plan review for structural work: no standard time is published. A permit that needs plans isn't issued until plan review is done.
What changes on January 1, 2027
Two state changes land on New Year's Day, and they apply in New Orleans like everywhere else.
First, the code edition. The LSUCCC says the 2024 ICC codes and the 2023 National Electrical Code become effective January 1, 2027, replacing the 2021 codes and 2020 NEC in force now. The commission's August 2026 notice in the Louisiana Register keeps sprinkler mandates out of one- and two-family homes and assigns every parish to climate zone 2A for energy code purposes. If your drawings are being finished this winter, ask which edition they're drawn to.
Second, a new state fee. Kean Miller's summary of Act 881 of 2026 says the new Louisiana Uniform Construction Code Commission may collect up to $10 per permit, starting January 1, 2027. The same act says parishes and cities must enforce only the state code. Ten dollars won't change your budget, but it may show up as a new line on the permit invoice.
Inspections and the certificate of occupancy
You request inspections once the permit shows as Issued, and the city's inspections page says only contractors can request them. Requests go by email with the permit number and the type of inspection, and results post in the One Stop App. Building inspections include slab or foundation, rough framing, stormwater where it applies, and final. Electrical and mechanical work get a rough and a final. Plumbing inspections are booked through the Sewerage and Water Board.
Re-roofing works differently. There's no site visit. The contractor uploads geotagged photos at four stages: tear-off, underlayment, drip edge and flashing, and the finished roof. Licensed third-party inspectors can handle some inspections for a separate fee.
The permit fee covers normal inspections and the Certificate of Use and Occupancy, and a final inspection closes out the permit. Two rules worth knowing: the permit has to be posted where it can be seen from the street, and starting work before the permit is issued costs double the permit fee on top of the regular fees.
Who pulls the permit: the contractor
On a Jazzy Construction job, we pull the permit. It's part of the work, and Louisiana law puts that duty on the licensed contractor. R.S. 37:2160 bars a local building department from issuing a permit to anyone without an active license in the right classification. Under R.S. 37:2158, it's a violation to start before the permit is issued, to misstate the value or scope on the application, or to skip required inspections.
A homeowner working on their own residence can claim the owner exemption by signing the board's affidavit at the permit office. But if a contractor asks you to pull the permit in your name for work they're doing, treat it as a red flag. Our Louisiana contractor license lookup guide shows how to check what a contractor is licensed for.
Getting a permit in Jefferson Parish
Across the parish line, Jefferson runs its own offices. Its building permit pages list an East Bank office at the Joseph S. Yenni Building, 1221 Elmwood Park Boulevard, Suite 101, and a West Bank office at 1855 Ames Boulevard, Suite A, in Marrero. The parish encourages applying online. Cities inside the parish may have their own office, so check which one covers your address.
The parish's residential permitting requirements call for a current stamped survey, plus stamped plans by a registered architect or civil engineer for new homes and additions. The owner of a personal residence or the owner's contractor may apply. An owner signs an affidavit claiming exemption; a contractor needs a Louisiana residential license, and a home improvement contractor also needs a Jefferson Parish home improvement license. Within 1,500 feet of the Mississippi River levee, or 300 feet of any other levee, you'll need a levee district permit too.
For roofs, the parish introduced a re-roofing permit in August 2023 for one- and two-family homes in unincorporated areas when half or more of the roof covering is replaced. The 2023 release set the fee at $50 and swapped the site inspection for geotagged photos. The parish's building regulatory division says electrical, plumbing and mechanical work need filings by licensed trades.
Outside the metro, and parade season
Every parish and city in Louisiana has its own permit office and fee schedule, and the state contractor license applies in all of them. Some rules are statewide. The LSLBC's August 2025 roofing memo notes that Act 239 of 2025 requires a permit and inspections for roof construction and reroofing on projects begun on or after August 1, 2025. We're licensed statewide, we take projects across Louisiana, and we deal with the permit office wherever the house is. Our guide to hiring a general contractor in Louisiana links each city's office.
In New Orleans, Carnival raises its own scheduling question. The city's parade route rules say scaffolding and platforms are prohibited along the route at all times. We didn't find an official city rule on dumpsters or deliveries near routes, so if your house is on or near one, ask the city before the season. We plan around it at the walkthrough. Get an estimate.
Common questions
- Do I need a permit to replace my roof in New Orleans?
- Yes, if the work affects 50 percent or more of the roof on a single- or two-family home. The city requires a residential re-roofing permit through the One Stop App, and historic district properties get extra review. Smaller repairs are generally exempt unless they replace sheathing or meet other permit criteria.
- Who pulls a New Orleans building permit, the homeowner or the contractor?
- On a contracted job, the licensed contractor pulls it. Louisiana law bars permit offices from issuing a permit to anyone without an active license in the right classification. A homeowner working on their own residence can apply as owner by signing the state exemption affidavit.
- How much does a building permit cost in New Orleans?
- As of November 2026, the city's guide lists $60 plus $5 per $1,000 of work value, with plan review at $1 per $1,000 (minimum $60) when plans are needed. Historic district properties pay a 50 percent surcharge. From January 1, 2027, Act 881 lets the state commission add a fee of up to $10 per permit.
- What building code applies in New Orleans in 2027?
- The state's code commission says the 2024 ICC codes and the 2023 National Electrical Code take effect January 1, 2027. Act 881 of 2026 requires parishes and cities to enforce only the state code. Ask your contractor which edition your drawings follow if the job spans the change.
- How long does HDLC approval take?
- The HDLC says staff review of a Certificate of Appropriateness takes about 3 to 5 days. Its Express Lane issues certificates for qualifying work, such as roof replacement and repairs to match existing, within 1 to 3 business days. Committee or full Commission review takes longer, with no fixed time published.
- Is the New Orleans permitting concierge open to homeowners?
- Not as announced. Fox 8 reported in September 2026 that the pilot assigns two Safety and Permits staffers to help businesses along the Chef Menteur Industrial Corridor and the Canal Corridor. A residential permit still goes through the One Stop App.
Sources
- City of New Orleans, Guide to Building Permits
- City of New Orleans, Work exempt from building permits
- City of New Orleans, Residential re-roofing permit
- City of New Orleans, Inspections
- HDLC, Certificate of Appropriateness
- HDLC Express Lane
- Vieux Carre Commission, Application process
- One Stop App
- Fox 8, New Orleans will launch new streamlined permitting program (September 24, 2026)
- LSUCCC, Louisiana construction code information
- Louisiana Register notice of intent, 2024 I-codes (August 2026)
- Kean Miller, Act 120 of 2025 and Act 881 of 2026
- Jefferson Parish, Residential permitting requirements
- Jefferson Parish, Building permits
- Jefferson Parish, Re-roofing permit release, August 2023
- Jefferson Parish, Building Regulatory Division
- La. R.S. 37:2160, permits and local authority
- La. R.S. 37:2158, contractor violations
- LSLBC memo to roofing contractors, August 2025
- NOLA Ready, Along the parade route
Rules, programs and prices change. Check the source before you rely on a figure, and ask us to confirm it for your property.